Cadeler secured the full installation scope of all 114 Vestas V164-10.0MW turbine generators (WTGs) at the Seagreen offshore wind farm in Scotland. When the wind farm was completed in June 2023, it took the record as Scotland’s largest and the world’s deepest fixed bottom offshore wind farm.
During this project, we installed some of the deepest fixed wind turbines that we have ever installed in the history of Cadeler. On 25 locations the water depth exceeded 55 metres with the deepest installed having a water depth of an impressive 59 metres.
These deep locations have been an area of focus since the early preparation days in 2019. A result of many hours of well-researched location specific engineering, planning, and of course the good collaboration between Cadeler, Vestas, SSE Renewables and TotalEnergies.
Today, the Seagreen offshore wind farm is making an impactful contribution to the green transition in the UK where it generates around 5,000 GWh a year, enough to power more than 1.6 million homes with green and clean energy.
The 1.075MW wind farm is owned by TotalEnergies and SSE Renewables. It is located off the coast of Angus in the North Sea. Wind Orca was deployed for this installation and load out port was Port of Nigg.